This procedure allows you to setup a stage gate as a stage gate activation step. Once a stage gate set as a stage gate activation step, a log entry appears in the Stage Gate Setup Log panel. After the project activation gate is approved during the stage gate process, the project becomes active.
If a stage gate activation gate is not set; by default, the last stage gate is considered as a stage gate activation step.
-
Navigate to Admin > Portfolios Admin > Stage Gates Setup.
-
Click the Actions list and select Set Project Activation Gate.
The Set Project Activation Gate dialog box appears.
-
Click the Stage Gate Process ellipsis to select the required stage gate process.
-
Click the Stage Gate Activation Step ellipsis to select the required stage gate.
-
(Optional) Type a Comment.
-
Click the Run button. The Set Project Activation Gate confirmation dialog box appears.
-
Click the OK button.