The Productivity Factor can be calculated for contract lines having a Current Productivity forecasting method.

  1. Navigate to Forecasts > Contract Forecast.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.

  3. Click Refresh for screen update.

  4. Click the Contract Forecast tab.

  5. View the Productivity Factor value for contract line with Current Productivity forecast method. Productivity Factor is updated using the formula: VOWD Cost / AC Cost.