This procedure allows you to update the project schedule enterprise calendars. You can select the required time zone and define the working days and duration of resources.
-
Navigate to Admin > Projects Admin > Project Schedule Admin.
-
Click the Calendars tab.
-
Click the Insert Row icon.
-
Type in the Calendar ID.
-
Type in the Calendar Name.
-
Type in the Timezone.
-
Enter the Start Hour and Start Minute of the project schedule.
-
Enter the project Duration (Hours).
-
Select the required work day check box to select the working days in a week.
-
Click SAVE. The Timezone field auto-updates as UTC by default. Also, the Update hyperlink appears in the Update Timezone field.
-
Click the Update hyperlink.
-
Click the Timezone ellipsis and select the timezone that you want to assign to the particular calendar.
-
Click RUN and then OK.