Backout Production Time Sheet - EcoSys - 4.02 - Administration & Configuration - Hexagon PPM

EcoSys Core and Projects Administration (4.02)

Language
English
Product
EcoSys
Search by Category
Administration & Configuration
EcoSys Standard Version
4.02

This procedure allows you to backout the timesheet entries from production to staging for a selected project.

  1. Click the Actions list and select Backout Production Timesheet.

  2. Click the ellipsis and select the required value.

    • Project - Select the project for which you want to backout production timesheet.

    • Tracking Period - Select the time period for which you want to backout the timesheet entries.

    • Resource - Select the resource whose timesheet needs to be backed out.

  3. (Optional) Type in your Comment for backing out the time entries.

  4. Click RUN and then OK.