View and Update Admin Projects - EcoSys - 4.01 - Administration & Configuration - Hexagon PPM

EcoSys Core and Projects Administration (4.01)

Language
English
Product
EcoSys
Search by Category
Administration & Configuration
EcoSys Standard Version
4.01

This process allows you to view and create administrative projects for resources to submit timesheets towards Paid Time Off (PTO) and Holidays.

  1. Click the Admin Projects tab.

  2. Click the Insert Row icon to add a new row for the administrative project.

  3. Type an ID and Name for the administrative project.

  4. Click the ellipsis and select the required value.

    • Type - Select the type of project.

    • Parent Path ID - Select the parent for the administrative project.

    • (Optional) Cost Control Level - Select Yes.

      This determines what level of entry a user can input within their timesheets.

  5. Click SAVE.

    • The administrative project "04 – Holiday" is hard coded throughout the product and is not recommended for deletion.

    • To remove a time off project, click the Delete Row(s) icon.

    • You can customize the view of the Maintain WBS Structure panel from the view settings.