All change time-phased results can be viewed on the Time-Phasing tab, regardless of change status. Follow the procedure below to review the results of either manual or systematic time-phasing.

  1. Navigate to Changes > Contract Changes.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.

  3. If required, click REFRESH to update the screen.

  4. Click the Contract Change Register tab.

  5. Click the Contract Change ID hyperlink. The Contract Change Details panel appears.

  6. Click the Time-Phasing tab.

  7. Select the Start Period and End Period to update the time-phasing data of the selected period.

    If the curve type is not Manual, time-phasing contract change details will be protected and cannot be updated.