This procedure allows you to view the VOWD before or after VOWD generation.

  1. Navigate to Progress > Contract Value of Work Done.

  2. At the top of the screen, in the green parameter bar, click the Contract and Contract Period ellipsis to select the required contract and period.

  3. Click Refresh for screen update.

  4. Click the Contract Progress tab.