This procedure allows you to create a lesson learned. For each lesson learned a Lesson ID is generated by the system. The lesson IDs are managed by the structure in the Contract Setup screen (Contracts > Contract Setup > Contract Register - Register Admin tab). After creating a lesson learned, a log entry appears in the Log tab.

  1. Navigate to Contracts > Lesson Learned.

  2. Click the Actions list and select Create Lesson Learned.

  3. Click the Contract ellipsis and select the required contract. By default, the last selected contract appears.

    The Contract displayed in the green parameter bar at the top of the screen is the only contract available for selection in the Create Lesson Learned dialog box.

  4. Type in the required Lesson Learned Name.

  5. Click RUN and then OK.