The Productivity Factor can be calculated for contract lines having a Current Productivity forecasting method.
-
Navigate to Forecasts > Contract Forecast.
-
At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.
-
Click Refresh for screen update.
-
Click the Contract Forecast tab.
-
View the Productivity Factor value for contract line with Current Productivity forecast method. Productivity Factor is updated using the formula: VOWD Cost / AC Cost.