This procedure allows you to change the status of the contract change request to Open. Any contract change that belongs to an active contract can be re-opened. Contract changes with an Open status can be updated. An event entry is added to the contract change log, and all resources (users) established in the Contract Setup screen (Contracts > Contract Setup > Contract Register > Contract Details – Workflow Admin) with a Distribution List value of All Contract Workflow or Change Workflow will be notified.

  1. Navigate to Changes > Contract Changes.

  2. Click the Actions list and select Re-Open Change.

  3. Click the Contract ellipsis to select the required contract.

  4. Click the Contract Change ellipsis to select the required contract change.

  5. (Optional) Type in a Comment.

  6. Click RUN and then OK.