All change time-phased results can be viewed on the Time-Phasing tab, regardless of change status. Follow the procedure below to review the results of either manual or systematic time-phasing.
-
Navigate to Changes > Contract Changes.
-
At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.
-
If required, click REFRESH to update the screen.
-
Click the Contract Change Register tab.
-
Click the Contract Change ID hyperlink. The Contract Change Details panel appears.
-
Click the Time-Phasing tab.
-
Select the Start Period and End Period to update the time-phasing data of the selected period.
If the curve type is not Manual, time-phasing contract change details will be protected and cannot be updated.