This procedure allows you to establish the contract start date, end date, curve, and Units of Measurement (UOM) for all the contract line items.

  1. Navigate to Budgets > Contract Budget.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required project.

  3. If required, click REFRESH to update the screen.

  4. Click the Contract Budget Register tab.

  5. Populate data as indicated below:

    1. (Optional) Start Date

    2. (Optional) End Date

    3. (Optional) Click the Curve ellipsis to select the budget curve. Budget curves include:

      • Back Loaded

      • Bell Curve

      • Front Loaded

      • Linear

      • Manual

    4. (Optional) UOM

    5. Click the Save icon.

      You can customize the view of the Line Item Register panel from the view settings.