Before Physical % Complete can be updated, the Progress Method for the Contract Line must be set to Physical % Complete and the Contract Progress spreadsheet must be saved.

  1. Navigate to Progress > Contract Value of Work Done.

  2. At the top of the screen, in the green parameter bar, click the Contract and Contract Period ellipsis to select the required contract and period.

  3. Click Refresh for screen update.

  4. Click the Contract Progress tab.

  5. Edit the Physical % Complete.

  6. Click the Save icon.