Systematic (non-manual) time-phasing is performed using the Time-Phase Open Budget action. This action will spread the quantities, hours, and costs based upon the Contract Line Start Date, End Date, and Curve displayed in the Original Budget tab that have a Curve Type of "Back Loaded", "Front Loaded, "Bell", or "Linear".

  1. Navigate to Budgets > Contract Budget.

  2. Click the Actions list and select Time-Phase Open Budget.

  3. Click the Contract ellipsis to select the required Contract and then click RUN.

  4. Click OK and then REFRESH. The time-phased budget appears in the Contract Budget Manual panel.