Create the PBS - HxGN SDx - Update 64 - Administration & Configuration

Administration and Configuration of HxGN SDx

Language
English
Product
HxGN SDx
Search by Category
Administration & Configuration
SmartPlant Foundation / SDx Version
10

For the Hexagon default hierarchy, the PBS can be created interactively or using the Load Manager. For the cross-plant hierarchy, the PBS must be created using the Load Manager.

What order and what option should I use to create my PBS?

Step

Set your Create Scope to

To create a Hexagon default PBS

To create a cross-plant interaction PBS

Using the Load Manager

Interactively

Using the Load Manager

Interactively

1

Config Top

Load Sites

Create Site

Load Sites

N/A

2

Config Top

Load Plants

Create Plant

Load Plants

N/A

3

Plant created in step 2

Load Areas (SDx)

Create Area

Load Areas (CFIHOS)

N/A

4

Plant created in step 2

Load Units (SDx)

Create Unit

Load Units (CFIHOS)

N/A